Brown
Brown
Good Service
Updated 10:08 PM CDT
Reliability — last 30 days
Recent status changes
- Jul 28, 7:43 PM Good Service Good Service
- Jul 28, 7:14 PM Minor Delays Minor Delays — Kimball-bound Brown and Linden-bound Purple Line trains are standing at Belmont due to a door problem. Crews working to restore service.
- Jul 28, 4:58 PM Good Service Good Service
- Jul 28, 4:35 PM Suspended Major Delays — Kimball-bound Brown Line trains are running w/major delays following an earlier mechanical problem near Wellington. Service is resuming, allow extra time.
- Jul 27, 3:00 AM Good Service Good Service
- Jul 26, 7:53 PM Severe Delays Planned Work w/Part Closure — Orange, Green, Pink and Brown Line trains will be rerouted downtown for work on building a new State/Lake station.
- Jul 26, 7:41 PM Suspended Major Delays — Brown Line trains are standing near Kimball due to a signal problem. Crews working to restore service.
- Jul 26, 3:32 PM Severe Delays Planned Work w/Part Closure — Orange, Green, Pink and Brown Line trains will be rerouted downtown for work on building a new State/Lake station.
- Jul 26, 3:03 PM Suspended Major Delays — Loop "L" Line trains are running w/residual delays following an earlier sick passenger at Washington/Wells. Service is resuming, allow extra time.
- Jul 25, 2:00 AM Severe Delays Planned Work w/Part Closure — Orange, Green, Pink and Brown Line trains will be rerouted downtown for work on building a new State/Lake station.
- Jul 24, 9:31 AM Good Service Good Service
- Jul 24, 9:00 AM Minor Delays Minor Delays — Green, Pink, Orange and Brown Line trains are standing near the Roosevelt due to a report of a minor fire at track level. Crews working to restore service.
- Jul 23, 3:13 AM Good Service Good Service
- Jul 23, 3:09 AM Status Unavailable Status Unavailable
- Jul 20, 2:51 PM Good Service Good Service
- Jul 20, 2:42 PM Minor Delays Minor Delays — Loop-bound Brown and Purple Line trains are standing near Wellington due to a mechanical problem. Crews working to restore service.
- Jul 20, 3:00 AM Good Service Good Service
- Jul 18, 2:01 AM Severe Delays Planned Work w/Part Closure — Orange, Green, Pink and Brown Line trains will be rerouted downtown for work on building a new State/Lake station.
- Jul 17, 2:43 PM Good Service Good Service
- Jul 16, 12:50 AM Planned Work Service Change — Brown/Orange/Purple line trains will be reduced to 4-car lengths on weekends without major events or construction (3:30a Sat to 3:30a Mon).